| Excavation (if any) |
100 |
07-Oct-2024 |
| Basements (if any) |
95 |
25-Jul-2027 |
| Podiums (if any) |
0 |
14-Nov-2028 |
| Plinth |
100 |
10-Sep-2024 |
| Stilt Floor |
0 |
14-Nov-2028 |
| Slabs of Super Structure |
90 |
10-Mar-2027 |
| Internal walls, plaster, floorings, doors and windows |
20 |
22-Jul-2027 |
| Sanitary and Electrical Fittings |
5 |
25-Apr-2028 |
| Staircases, Lifts Wells, Lobbies, Overhead and Underground Water Tanks |
50 |
30-Jul-2027 |
| External plumbing, plaster, elevation, and waterproofing |
0 |
12-May-2028 |
| Installation of Lifts, water pumps, and Fire Fighting Equipment |
10 |
12-Nov-2028 |
| N.O.C, Electrical fittings, Mechanical Equipment, and environmental compliance |
0 |
12-Nov-2028 |
| Internal Roads & Footpaths Proposed |
|
| Finishing to entrance lobby, plinth protection, paving, compound wall, and other activities |
20 |
12-Nov-2028 |
| Overall Percentage of Actual Work Done |
52 |
Overall Final Completion Date: 12-Nov-2028 |