Project Details
| Project Name |
:
|
HASHMI RESIDENCY
|
Project Description |
:
|
RESIDENTIAL COMPLEX CONSISTING 3 FLOORS
|
| Project Type
|
:
|
Residential/Group Housing
|
Project Status
|
:
|
Completed
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
20-12-2018
|
Project End Date |
:
|
30-06-2022
|
| Total Area of Land (Sq mt) |
:
|
1011.55
|
Total Open Area (Sq. Mtr.) |
:
|
372.16
|
| Total Covered Area (Sq Mtr) |
:
|
639.39
|
Total Builtup Area (Sq. Mtr.) |
:
|
2001.39
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
300.00
|
Estimated cost of land (In Lakh) |
:
|
264.06
|
| Project Address
|
:
|
CHITKOHRA,NEAR EMAARAT AL- AZIZ,P.S-GARDANIBAGH PATNA 800002
|
District |
:
|
Patna
|
| Khesra No./Plot No. |
:
|
145 $ 146 (P)
|
| Block |
:
|
Patna Sadar
|
Mauja |
:
|
चितकोहरा
|
| Village |
:
|
|
City/Town |
:
|
PATNA
|
| Boundaries (East) |
:
|
NASRU MIYA
|
Boundaries (West) |
:
|
ROAD
|
| Boundaries (North) |
:
|
ZAHIDA KHATUN
|
Boundaries (South) |
:
|
NIJ ( SHAHID HASHMI)
|
| Latitude of End point of the plot |
:
|
0
|
Longitude of End point of the plot |
:
|
0
|
| No. of Garages Available for Sale |
:
|
23
|
Total Area of Garages (Sq Mtr) |
:
|
525.85
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
23
|
Total Area of Covered Parking (Sq Mtr) |
:
|
525.85
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
42
|
| Permissible FAR |
:
|
2.00
|
Sanctioned FAR |
:
|
1.99
|
| Proposed No of Building or Wing |
:
|
1
|
Sanctioned No of Building(s) or Wing(s) |
:
|
1
|
| Aggregate area of the recreational open space |
:
|
0.00
|
Architecture/Design standards used |
:
|
INDIAN STANDARD
|
| Type of construction technology used |
:
|
R.C.C FRAMED STRUCTURE
|
Earthquake resistant measures adopted for building and common areas |
:
|
ZONE 4
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
| |
| Name of Building | Sanctioned No of Floor | Type of Apartment | No of Apartment | Carpet Area | Area of exclusive balcony | Area of exclusive open terrace |
| HASHMI RESIDENCY | B+G+3 | 2 BHK | 9 | 6319.00 | 270.29 | 6319.00 |
| HASHMI RESIDENCY | B+G+3 | 3 BHK | 14 | 12950.00 | 408.29 | 12950.00 |
|
|
| Road System |
:
|
Local Authority
|
Water Supply |
:
|
Local Authority
|
| Sewage and Drainage System |
:
|
Local Authority
|
Electricity Supply Transformer And Sub Station |
:
|
Local Authority
|
| Solid Waste Management and Disposal |
:
|
Local Authority
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
Axis Bank
|
Branch Name |
:
|
ANISABAD
|
| Account No. |
:
|
916020055037130
|
IFSC Code |
:
|
UTIB0001664
|
| Bank Address |
: |
{"BRANCH":"ANISABAD","CONTACT":"","RTGS":true,"STATE":"BIHAR","ADDRESS":"UFO MALL, ANISABAD, NEAR ANISABAD CHOWRAHA, PATNA, BIHAR, PIN 800002","CITY":"PATNA","DISTRICT":"PATNA","BANK":"Axis Bank","BANKCODE":"UTIB","IFSC":"UTIB0001664"}
|
| State |
:
|
Bihar
|
District |
:
|
Patna
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
| Project Name | Financial Year | Quarter | Uploaded Date | Quarterly Progress In PDF | Quarterly Progress Image | Quarterly Progress Image |
| HASHMI RESIDENCY | 2021-2022 | Q3-Oct to Dec | 09 Feb 2022 |
View Document
|
|
|
| HASHMI RESIDENCY | 2021-2022 | Q2-Jul to Sep | 12 Oct 2021 |
View Document
|
|
|
| HASHMI RESIDENCY | 2020-2021 | Q1-Apr to Jun | 25 Sep 2020 |
View Document
|
|
|
| HASHMI RESIDENCY | 2019-2020 | Q4-Jan to Mar | 25 Sep 2020 |
View Document
|
|
|
| HASHMI RESIDENCY | 2019-2020 | Q1-Apr to Jun | 03 Aug 2019 |
View Document
|
|
|
|
|
|