Project Details
| Project Name |
:
|
Sri Sai Laxmi Grih Enclave
|
Project Description |
:
|
On the land of Sr Chaitu Singh & other at Mauza- Mainpura,Thana, Patliputra, Thana no.2, Tauzi-5123, Khata-256, Plot no. 1785(P), own & Dist. Patna
|
| Project Type
|
:
|
Residential/Group Housing
|
Project Status
|
:
|
New Project Launch
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
15-11-2018
|
Project End Date |
:
|
31-07-2021
|
| Total Area of Land (Sq mt) |
:
|
1561.86
|
Total Open Area (Sq. Mtr.) |
:
|
736.78
|
| Total Covered Area (Sq Mtr) |
:
|
750.50
|
Total Builtup Area (Sq. Mtr.) |
:
|
2400.41
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
360.00
|
Estimated cost of land (In Lakh) |
:
|
350.00
|
| Project Address
|
:
|
On the land of Sr Chaitu Singh & other at Mauza- Mainpura,Thana, Patliputra, Thana no.2, Tauzi-5123, Khata-256, Plot no. 1785(P), own & Dist. Patna
|
District |
:
|
Patna
|
| Khesra No./Plot No. |
:
|
1785(P)
|
| Block |
:
|
Patna Sadar
|
Mauja |
:
|
मैनपुरा
|
| Village |
:
|
Patna
|
City/Town |
:
|
Patna
|
| Boundaries (East) |
:
|
Kalter Rai
|
Boundaries (West) |
:
|
Nag Singh, Jham Lal Singh & Road
|
| Boundaries (North) |
:
|
Self land
|
Boundaries (South) |
:
|
Sub Road
|
| Latitude of End point of the plot |
:
|
25.6275
|
Longitude of End point of the plot |
:
|
85.1207
|
| No. of Garages Available for Sale |
:
|
38
|
Total Area of Garages (Sq Mtr) |
:
|
601.59
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
38
|
Total Area of Covered Parking (Sq Mtr) |
:
|
601.59
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
36
|
| Permissible FAR |
:
|
2.00
|
Sanctioned FAR |
:
|
1.61
|
| Proposed No of Building or Wing |
:
|
1
|
Sanctioned No of Building(s) or Wing(s) |
:
|
1
|
| Aggregate area of the recreational open space |
:
|
100.00
|
Architecture/Design standards used |
:
|
YES
|
| Type of construction technology used |
:
|
FRAME STRUCTURE / ISOLATED & RAFT FOUNDATION
|
Earthquake resistant measures adopted for building and common areas |
:
|
YES
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
| |
| Name of Building | Sanctioned No of Floor | Type of Apartment | No of Apartment | Carpet Area | Area of exclusive balcony | Area of exclusive open terrace |
| Sri Sai Grih Laxmi Enclave | G + 3 | 2 BHK | 20 | 11621.00 | 732.00 | 1758.00 |
| Sri Sai Grih Laxmi Enclave | G + 3 | 1 BHK | 6 | 2016.00 | 2016.00 | 0.00 |
| Sri Sai Grih Laxmi Enclave | G + 3 | 3 BHK | 12 | 8550.00 | 1359.00 | 3828.00 |
|
|
| Road System |
:
|
Local Authority
|
Water Supply |
:
|
Self Development
|
| Sewage and Drainage System |
:
|
Local Authority
|
Electricity Supply Transformer And Sub Station |
:
|
Self Development
|
| Solid Waste Management and Disposal |
:
|
Local Authority
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
Bank of Baroda
|
Branch Name |
:
|
PATEL NAGAR, PATNA
|
| Account No. |
:
|
52570200000216
|
IFSC Code |
:
|
BARB0PATELN
|
| Bank Address |
: |
{"RTGS":true,"CONTACT":"1800223344","BRANCH":"PATEL NAGAR","DISTRICT":"PATNA","CITY":"PATNA","STATE":"BIHAR","ADDRESS":"SAHDEOPATH B BHATTACHARYA ROAD WEST PATEL NAGAR PO SHASTRI NAGAR TEHSIL SADAR PATNA BIHAR 800023","BANK":"Bank of Baroda","BANKCODE":"BARB","IFSC":"BARB0PATELN"}
|
| State |
:
|
Bihar
|
District |
:
|
Patna
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Vendor Type | Name | Address | State | District | Year of Establishment | Key Project |
| Engineers | Shailendra Kumar | Patna Municipal corporation, Enrollment No.-SE/06/15 | Bihar | Patna | 2010 | 2021 |
| Architects | RAJESH PASWAN | Patna Nagar Nigam registered architect. Patna | Bihar | Patna | 2015 | 20 |
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
|
|
|
|