Project Details
| Project Name |
:
|
JAWAHAR MALL AND RESIDENCY
|
Project Description |
:
|
IT IS LB+UB+G+6 APPROVED RESIDENTIAL -CUM-COMMERCIAL BUILDING
|
| Project Type
|
:
|
Mixed Development(residential and commercial)
|
Project Status
|
:
|
New Project Launch
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
01-12-2024
|
Project End Date |
:
|
30-09-2029
|
| Total Area of Land (Sq mt) |
:
|
2555.36
|
Total Open Area (Sq. Mtr.) |
:
|
1339.18
|
| Total Covered Area (Sq Mtr) |
:
|
1216.18
|
Total Builtup Area (Sq. Mtr.) |
:
|
9626.24
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
1800.64
|
Estimated cost of land (In Lakh) |
:
|
0.00
|
| Project Address
|
:
|
BHAGWAN MAHAVIR PATH, NATH NAGAR, BHAGALPUR, BIHAR
|
District |
:
|
Bhagalpur
|
| Khesra No./Plot No. |
:
|
1244,KA,KHA,GA,GHA,JHA,TA
|
| Block |
:
|
Nathnagar
|
Mauja |
:
|
वार्ड न. 19
|
| Village |
:
|
|
City/Town |
:
|
BHAGALPUR
|
| Boundaries (East) |
:
|
RAJENDRA SINGH, SHAMBHU SINGH OTHERS
|
Boundaries (West) |
:
|
MAHESH YADAV, PRADEEP MANDAL OTHERS
|
| Boundaries (North) |
:
|
NASRATKHANI-AMARKANT MANDAL OTHERS
|
Boundaries (South) |
:
|
BHAGWAN MAHAVIR PATH
|
| Latitude of End point of the plot |
:
|
25.240319
|
Longitude of End point of the plot |
:
|
86.94168
|
| No. of Garages Available for Sale |
:
|
0
|
Total Area of Garages (Sq Mtr) |
:
|
0.00
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
30
|
Total Area of Covered Parking (Sq Mtr) |
:
|
3859.90
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
60
|
| Permissible FAR |
:
|
2.50
|
Sanctioned FAR |
:
|
2.40
|
| Proposed No of Building or Wing |
:
|
0
|
Sanctioned No of Building(s) or Wing(s) |
:
|
1
|
| Aggregate area of the recreational open space |
:
|
0.00
|
Architecture/Design standards used |
:
|
NBC
|
| Type of construction technology used |
:
|
RCC FRAME STRUCTURE
|
Earthquake resistant measures adopted for building and common areas |
:
|
AS PER IS CODE
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
| |
| Name of Building | Sanctioned No of Floor | Type of Apartment | No of Apartment | Carpet Area | Area of exclusive balcony | Area of exclusive open terrace |
| JAWAHAR MALL & RESIDENCY | B+UB+G+6 | Shop | 06 | 1138.00 | 0.00 | 0.00 |
| JAWAHAR MALL & RESIDENCY | B+UB+G+6 | 3 BHK | 30 | 36768.00 | 6231.00 | 0.00 |
| JAWAHAR MALL & RESIDENCY | B+UB+G+6 | Shop | 02 | 222.00 | 0.00 | 0.00 |
| JAWAHAR MALL & RESIDENCY | B+UB+G+6 | Shop | 08 | 851.00 | 0.00 | 0.00 |
| JAWAHAR MALL & RESIDENCY | B+UB+G+6 | Office | 11 | 51272.00 | 0.00 | 0.00 |
|
|
| Road System |
:
|
Self Development
|
Water Supply |
:
|
Self Development
|
| Sewage and Drainage System |
:
|
Self Development
|
Electricity Supply Transformer And Sub Station |
:
|
Local Authority
|
| Solid Waste Management and Disposal |
:
|
Self Development
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
STATE BANK OF INDIA
|
Branch Name |
:
|
SATYAM COMPLEX, PBB, BHAGALPUR
|
| Account No. |
:
|
43379644377
|
IFSC Code |
:
|
SBIN0004385
|
| Bank Address |
: |
NULL
|
| State |
:
|
Bihar
|
District |
:
|
Bhagalpur
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Vendor Type | Name | Address | State | District | Year of Establishment | Key Project |
| Architects | ANUNAY ASHISH | BHAGALPUR, BIHAR | Bihar | Bhagalpur | 2020 | Residential and Commercial Project Completed |
| Engineers | MR SUSOBHAN KUNDU | Home Concept, Bhagalpur | Bihar | Bhagalpur | 2009 | Residential and Commercial Project Completed |
| Contractors | RIYAJUDDIN | Bhagalpur | Bihar | Bhagalpur | 2011 | Residential and Commercial Project Completed |
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
| Project Name | Financial Year | Quarter | Uploaded Date | Quarterly Progress In PDF | Quarterly Progress Image | Quarterly Progress Image |
| JAWAHAR MALL AND RESIDENCY | 2026-2027 | Q2 (Jul - Sep) | 25 Oct 2026 |
View Document
|
|
|
| JAWAHAR MALL AND RESIDENCY | 2026-2027 | Q1 (Apr - Jun) | 27 Jul 2026 |
View Document
|
|
|
| JAWAHAR MALL AND RESIDENCY | 2025-2026 | Q4 (Jan - Mar) | 29 Apr 2026 |
View Document
|
|
|
| JAWAHAR MALL AND RESIDENCY | 2025-2026 | Q3 (Oct - Dec) | 27 Jan 2026 |
View Document
|
|
|
| JAWAHAR MALL AND RESIDENCY | 2025-2026 | Q2 (Jul - Sep) | 30 Oct 2025 |
View Document
|
|
|
| JAWAHAR MALL AND RESIDENCY | 2025-2026 | Q1 (Apr - Jun) | 19 Aug 2025 |
View Document
|
|
|
|
|
|