Project Details
| Project Name |
:
|
Hari Mewa Complex
|
Project Description |
:
|
B+G+5, Residential Complex
|
| Project Type
|
:
|
Residential/Group Housing
|
Project Status
|
:
|
New Project Launch
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
16-02-2021
|
Project End Date |
:
|
31-03-2025
|
| Total Area of Land (Sq mt) |
:
|
3807.15
|
Total Open Area (Sq. Mtr.) |
:
|
2233.82
|
| Total Covered Area (Sq Mtr) |
:
|
1573.33
|
Total Builtup Area (Sq. Mtr.) |
:
|
7941.49
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
68240000.00
|
Estimated cost of land (In Lakh) |
:
|
59955000.00
|
| Project Address
|
:
|
Mauza, Bigrahpur, Survey Thana - Phulwari Sharif, at present P.S - Jakkanpur, Thana No. 22, Tauzi No. - 131, Khata No. 15
|
District |
:
|
Patna
|
| Khesra No./Plot No. |
:
|
74
|
| Block |
:
|
Phulwari Sarif
|
Mauja |
:
|
विग्रहपुर
|
| Village |
:
|
Bigrahpur
|
City/Town |
:
|
Patna
|
| Boundaries (East) |
:
|
Branch Road
|
Boundaries (West) |
:
|
Mahendra Prasad Singh and others
|
| Boundaries (North) |
:
|
Teka Ray and Other
|
Boundaries (South) |
:
|
Dahuaur Rai and Other
|
| Latitude of End point of the plot |
:
|
25.5871868
|
Longitude of End point of the plot |
:
|
85.1367681
|
| No. of Garages Available for Sale |
:
|
0
|
Total Area of Garages (Sq Mtr) |
:
|
0.00
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
248
|
Total Area of Covered Parking (Sq Mtr) |
:
|
3071.82
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
48
|
| Permissible FAR |
:
|
2.50
|
Sanctioned FAR |
:
|
2.09
|
| Proposed No of Building or Wing |
:
|
1
|
Sanctioned No of Building(s) or Wing(s) |
:
|
1
|
| Aggregate area of the recreational open space |
:
|
395.01
|
Architecture/Design standards used |
:
|
IS456:2000 NBS :2016, Bihar Building Byelaws' 2014
|
| Type of construction technology used |
:
|
RCC Framed Structure
|
Earthquake resistant measures adopted for building and common areas |
:
|
Building Designed for Zone IV
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
| |
| Name of Building | Sanctioned No of Floor | Type of Apartment | No of Apartment | Carpet Area | Area of exclusive balcony | Area of exclusive open terrace |
| Hari Mewa Complex | 7 | 3 BHK | 100 | 65726.60 | 0.00 | 0.00 |
|
|
| Road System |
:
|
Local Authority
|
Water Supply |
:
|
Self Development
|
| Sewage and Drainage System |
:
|
Self Development
|
Electricity Supply Transformer And Sub Station |
:
|
Local Authority
|
| Solid Waste Management and Disposal |
:
|
Local Authority
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
FEDERAL BANK OF INDIA
|
Branch Name |
:
|
Patna - 800001
|
| Account No. |
:
|
12200200025163
|
IFSC Code |
:
|
FDRL0001220
|
| Bank Address |
: |
{"BRANCH":"PATNA","CENTRE":"PATNA","DISTRICT":"PATNA","STATE":"BIHAR","ADDRESS":"P B NO. 164, NEW DAK BUNGLOW ROAD, , PATNA, 800 001, BIHAR","CONTACT":"2236045","UPI":true,"RTGS":true,"CITY":"PATNA","MICR":"800049002","NEFT":true,"IMPS":true,"BANK":"Federal Bank","BANKCODE":"FDRL","IFSC":"FDRL0001220"}
|
| State |
:
|
Bihar
|
District |
:
|
Patna
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Vendor Type | Name | Address | State | District | Year of Establishment | Key Project |
| Architects | Devashish | Flat no. 16, Mangaldeep, Apartment, Patliputra | Bihar | Patna | 2012 | Big Hospital, Patna, Shambhu Height |
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
| Project Name | Financial Year | Quarter | Uploaded Date | Quarterly Progress In PDF | Quarterly Progress Image | Quarterly Progress Image |
| Hari Mewa Complex | 2024-2025 | Q4-Jan to Mar | 08 Apr 2025 |
View Document
|
|
|
| Hari Mewa Complex | 2024-2025 | Q3-Oct to Dec | 19 Jan 2025 |
View Document
|
|
|
| Hari Mewa Complex | 2024-2025 | Q2-Jul to Sep | 16 Oct 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2024-2025 | Q1-Apr to Jun | 06 Aug 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2023-2024 | Q4-Jan to Mar | 25 Jul 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2023-2024 | Q3-Oct to Dec | 25 Jul 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2023-2024 | Q2-Jul to Sep | 25 Jul 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2023-2024 | Q1-Apr to Jun | 25 Jul 2024 |
View Document
|
|
|
| Hari Mewa Complex | 2022-2023 | Q3-Oct to Dec | 15 Jan 2023 |
View Document
|
|
|
| Hari Mewa Complex | 2022-2023 | Q2-Jul to Sep | 15 Oct 2022 |
View Document
|
|
|
| Hari Mewa Complex | 2022-2023 | Q1-Apr to Jun | 10 Aug 2022 |
View Document
|
|
|
| Hari Mewa Complex | 2021-2022 | Q4-Jan to Mar | 16 Jun 2022 |
View Document
|
|
|
| Hari Mewa Complex | 2021-2022 | Q3-Oct to Dec | 08 Mar 2022 |
View Document
|
|
|
| Hari Mewa Complex | 2021-2022 | Q2-Jul to Sep | 06 Nov 2021 |
View Document
|
|
|
|
|
|