| Case No | Name of Complainant | Promoter Name | Project Name | Complainant ID | Proceeding Date | Proceeding Documents | Status |
| Ex. Case No.285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 07 Aug 2023 |
View
| Hearing Stage (Court Proceeding) |
| Execution Case No. 285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 16 Jan 2024 |
View
| Order/judgment |
| Ex. Case No.285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 23 Nov 2023 |
View
| Hearing Stage (Court Proceeding) |
| RERA/CC-128/2018/Execution Case No.199/2021 | Shabbir Ahmad | SAEBAN CONSTRUCTION PVT. LTD. | SAEBAN RESIDENCY | RERAC11202018144456 | 13 Sep 2022 |
View
| Hearing Stage (Court Proceeding) |
| Execution Case No. 285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 22 Sep 2023 |
View
| Hearing Stage (Court Proceeding) |
| RERA/CC-128/2018/Execution Case No.199/2021 | Shabbir Ahmad | SAEBAN CONSTRUCTION PVT. LTD. | SAEBAN RESIDENCY | RERAC11202018144456 | 13 Sep 2022 |
View
| Hearing Stage (Court Proceeding) |
| Execution Case No. 285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 16 Jan 2024 |
View
| Order/judgment |
| rera/cc/820/2021/Execution Case No. 285/2022 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 01 Dec 2022 |
View
| Hearing Stage (Court Proceeding) |
| Ex. Case No.285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 18 Apr 2023 |
View
| Hearing Stage (Court Proceeding) |
| Ex. Case No.285/2022 RERA/CC/820/2021 | Syed Shahab Ashraf | Saeban Construction Pvt. Ltd | Saeban Residency | RERAC08012021020432 | 23 May 2023 |
View
| Hearing Stage (Court Proceeding) |
|