Project Details
| Project Name |
:
|
Vastu Kiran Phase 1
|
Project Description |
:
|
A township project consist of 8 individual banglow/unit along with other amenities there on.
|
| Project Type
|
:
|
Residential/Group Housing
|
Project Status
|
:
|
New Project Launch
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
01-03-2020
|
Project End Date |
:
|
28-02-2022
|
| Total Area of Land (Sq mt) |
:
|
1093.65
|
Total Open Area (Sq. Mtr.) |
:
|
185.80
|
| Total Covered Area (Sq Mtr) |
:
|
907.85
|
Total Builtup Area (Sq. Mtr.) |
:
|
1106.28
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
117.72
|
Estimated cost of land (In Lakh) |
:
|
43.26
|
| Project Address
|
:
|
Near Ashok Dham temple , Ward No.-1 Mouza - Chouki, Lakhisarai
|
District |
:
|
Lakhisarai
|
| Khesra No./Plot No. |
:
|
288
|
| Block |
:
|
Lakhisarai
|
Mauja |
:
|
चौकी
|
| Village |
:
|
|
City/Town |
:
|
|
| Boundaries (East) |
:
|
Darwari Singh
|
Boundaries (West) |
:
|
Kunja Singh
|
| Boundaries (North) |
:
|
Kunja Singh
|
Boundaries (South) |
:
|
Road
|
| Latitude of End point of the plot |
:
|
25.1928833
|
Longitude of End point of the plot |
:
|
86.069878
|
| No. of Garages Available for Sale |
:
|
0
|
Total Area of Garages (Sq Mtr) |
:
|
0.00
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
8
|
Total Area of Covered Parking (Sq Mtr) |
:
|
71.35
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
48
|
| Permissible FAR |
:
|
2.15
|
Sanctioned FAR |
:
|
2.15
|
| Proposed No of Building or Wing |
:
|
8
|
Sanctioned No of Building(s) or Wing(s) |
:
|
8
|
| Aggregate area of the recreational open space |
:
|
185.80
|
Architecture/Design standards used |
:
|
institutional India
|
| Type of construction technology used |
:
|
RCC Frame
|
Earthquake resistant measures adopted for building and common areas |
:
|
Yes
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
| |
| Name of Building | Sanctioned No of Floor | Type of Apartment | No of Apartment | Carpet Area | Area of exclusive balcony | Area of exclusive open terrace |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 284.76 | 54.89 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 323.68 | 87.50 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 325.78 | 98.25 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 327.56 | 98.50 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 326.33 | 88.00 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 225.80 | 60.75 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 235.26 | 70.00 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 327.21 | 98.50 | 0.00 |
| RUDRA KIRAN | 4 | 1 BHK | 03 | 326.21 | 88.00 | 0.00 |
|
|
| Road System |
:
|
Self Development
|
Water Supply |
:
|
Self Development
|
| Sewage and Drainage System |
:
|
Self Development
|
Electricity Supply Transformer And Sub Station |
:
|
Local Authority
|
| Solid Waste Management and Disposal |
:
|
Local Authority
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
Bandhan Bank
|
Branch Name |
:
|
lakhisarai
|
| Account No. |
:
|
10160004009826
|
IFSC Code |
:
|
BDBL0001307
|
| Bank Address |
: |
{"BRANCH":"LAKHI SARAI","CITY":"LAKHISARAI","UPI":true,"IMPS":true,"STATE":"BIHAR","ADDRESS":"DALPATTI MOHALLA,BAZAR SAMITI,P.O. & DIST.-LAKHI SARAI,BIHAR,PIN - 811311","CONTACT":"9801669053","NEFT":true,"DISTRICT":"PATNA","CENTRE":"PATNA","MICR":"811750102","RTGS":true,"BANK":"Bandhan Bank","BANKCODE":"BDBL","IFSC":"BDBL0001307"}
|
| State |
:
|
Bihar
|
District |
:
|
Lakhisarai
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Vendor Type | Name | Address | State | District | Year of Establishment | Key Project |
| Architects | SAMEER ANAND | LAKHISARAI | Bihar | Lakhisarai | 2014 | MANY |
| Architects | JATA SHANKAR KUMAR | LAKHISARAI | Bihar | Lakhisarai | 2018 | MANY |
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
| Project Name | Financial Year | Quarter | Uploaded Date | Quarterly Progress In PDF | Quarterly Progress Image | Quarterly Progress Image |
| Vastu Kiran Phase 1 | 2022-2023 | Q3-Oct to Dec | 15 Jan 2023 |
View Document
|
|
|
| Vastu Kiran Phase 1 | 2022-2023 | Q2-Jul to Sep | 29 Nov 2022 |
View Document
|
|
|
| Vastu Kiran Phase 1 | 2022-2023 | Q1-Apr to Jun | 20 Aug 2022 |
View Document
|
|
|
| Vastu Kiran Phase 1 | 2021-2022 | Q4-Jan to Mar | 19 Aug 2022 |
View Document
|
|
|
| Vastu Kiran Phase 1 | 2021-2022 | Q3-Oct to Dec | 19 Aug 2022 |
View Document
|
|
|
| Vastu Kiran Phase 1 | 2021-2022 | Q2-Jul to Sep | 18 Aug 2022 |
View Document
|
|
|
|
|
|