Project Details
| Project Name |
:
|
AARYAA ENCLAVE
|
Project Description |
:
|
ITS SITUATED AT KARJA-MUZAFFARPUR.
|
| Project Type
|
:
|
Plotted Development
|
Project Status
|
:
|
New Project Launch
|
| Reason for delayed |
:
|
|
No. of month (Delayed) |
:
|
|
| Project Start Date |
:
|
25-12-2019
|
Project End Date |
:
|
26-12-2024
|
| Total Area of Land (Sq mt) |
:
|
6615.42
|
Total Open Area (Sq. Mtr.) |
:
|
2033.40
|
| Total Covered Area (Sq Mtr) |
:
|
137589.44
|
Total Builtup Area (Sq. Mtr.) |
:
|
0.00
|
| If development is in phases |
:
|
0
|
No. of Phases
|
:
|
0
|
| |
|
|
Current Phase Area (Sq. Mtr.)
|
:
|
0.00
|
| Estimated cost of development (In Lakh) |
:
|
45.00
|
Estimated cost of land (In Lakh) |
:
|
190.00
|
| Project Address
|
:
|
VILL-NARHAR SARAI, P.S+P.O-KARJA, DIST-MUZAFFARPUR.
|
District |
:
|
|
| Khesra No./Plot No. |
:
|
1450,1471,1474,1421,1446,1741,1430,1429,1436,1443,1440,1445,1402,1444,1451
|
| Block |
:
|
|
Mauja |
:
|
|
| Village |
:
|
NARHAR SARAI
|
City/Town |
:
|
MUJAFFARPUR
|
| Boundaries (East) |
:
|
ROAD
|
Boundaries (West) |
:
|
N.H
|
| Boundaries (North) |
:
|
PROPOSED PLOT
|
Boundaries (South) |
:
|
PART PLOT
|
| Latitude of End point of the plot |
:
|
26.2624° N
|
Longitude of End point of the plot |
:
|
85.1194° E
|
| No. of Garages Available for Sale |
:
|
|
Total Area of Garages (Sq Mtr) |
:
|
0.00
|
| No. of Open Parking |
:
|
0
|
Total Area of Open Parking (Sq Mtr) |
:
|
0.00
|
| No. of Covered Parking |
:
|
|
Total Area of Covered Parking (Sq Mtr) |
:
|
0.00
|
| |
|
|
Proposed Period of Completion (In Month) |
:
|
60
|
| Permissible FAR |
:
|
0.00
|
Sanctioned FAR |
:
|
0.00
|
| Proposed No of Building or Wing |
:
|
|
Sanctioned No of Building(s) or Wing(s) |
:
|
|
| Aggregate area of the recreational open space |
:
|
0.00
|
Architecture/Design standards used |
:
|
|
| Type of construction technology used |
:
|
|
Earthquake resistant measures adopted for building and common areas |
:
|
|
|
Height of Building (Mtr.) |
: |
|
Coverage Area (Sqr. Mtr.) |
: |
|
|
| Road System |
:
|
Self Development
|
Water Supply |
:
|
Local Authority
|
| Sewage and Drainage System |
:
|
Local Authority
|
Electricity Supply Transformer And Sub Station |
:
|
Local Authority
|
| Solid Waste Management and Disposal |
:
|
Local Authority
|
|
|
|
| Account Holder Name |
:
|
|
|
|
|
| Bank Name |
:
|
Axis Bank
|
Branch Name |
:
|
MARIPUR, MUZAFFARPUR
|
| Account No. |
:
|
919020084854417
|
IFSC Code |
:
|
UTIB0001444
|
| Bank Address |
: |
{"CITY":"MUZAFFARPUR","STATE":"BIHAR","RTGS":true,"BRANCH":"MARIPUR","ADDRESS":"BISHNU PRASAD GUPTA MEMORIAL FOUNDATION,KAZIMOHMADPUR, MUZAFFARPUR,BIHAR , PIN 842001.","DISTRICT":"MUZAFFARPUR","IMPS":true,"NEFT":true,"CONTACT":"","CENTRE":"MUZAFFARPUR","MICR":"","BANK":"Axis Bank","BANKCODE":"UTIB","IFSC":"UTIB0001444"}
|
| State |
:
|
Bihar
|
District |
:
|
Muzaffarpur
|
| Scan copy of Bank Pass Book/ Statement |
:
|
View
|
|
|
|
| Vendor Type | Name | Address | State | District | Year of Establishment | Key Project |
| Architects | SAROJ KUMAR SINGH | PATNA | Bihar | Patna | 2005 | UP TO 50 PROJECTS |
|
| Sanctioned Building Plan (MAP) approved by : |
|
Date of approval (MAP) : |
|
| Period of approval (MAP) : |
|
|
|
| NOC approved by : |
|
Date of approval (NOC) : |
|
| |
|
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
Project Quarterly Progress
|
| Project Name | Financial Year | Quarter | Uploaded Date | Quarterly Progress In PDF | Quarterly Progress Image | Quarterly Progress Image |
| AARYAA ENCLAVE | 2023-2024 | Q1-Apr to Jun | 25 Jul 2024 |
View Document
|
|
|
| AARYAA ENCLAVE | 2022-2023 | Q4-Jan to Mar | 20 Apr 2023 |
View Document
|
|
|
| AARYAA ENCLAVE | 2022-2023 | Q3-Oct to Dec | 20 Apr 2023 |
View Document
|
|
|
| AARYAA ENCLAVE | 2022-2023 | Q2-Jul to Sep | 13 Oct 2022 |
View Document
|
|
|
| AARYAA ENCLAVE | 2022-2023 | Q1-Apr to Jun | 13 Oct 2022 |
View Document
|
|
|
| AARYAA ENCLAVE | 2021-2022 | Q4-Jan to Mar | 13 Oct 2022 |
View Document
|
|
|
| AARYAA ENCLAVE | 2021-2022 | Q3-Oct to Dec | 29 Jan 2022 |
View Document
|
|
|
| AARYAA ENCLAVE | 2021-2022 | Q2-Jul to Sep | 31 Dec 2021 |
View Document
|
|
|
| AARYAA ENCLAVE | 2021-2022 | Q1-Apr to Jun | 31 Dec 2021 |
View Document
|
|
|
| AARYAA ENCLAVE | 2020-2021 | Q4-Jan to Mar | 31 Dec 2021 |
View Document
|
|
|
| AARYAA ENCLAVE | 2020-2021 | Q3-Oct to Dec | 28 Feb 2021 |
View Document
|
|
|
| AARYAA ENCLAVE | 2020-2021 | Q2-Jul to Sep | 28 Feb 2021 |
View Document
|
|
|
| AARYAA ENCLAVE | 2020-2021 | Q1-Apr to Jun | 28 Feb 2021 |
View Document
|
|
|
|
|
|